Thursday, 10 January 2013

C. INSTALLATION

1 Pipes fittings completed.
 
2 Pipe properly supported.
 
3 Valves & components installed properly.
 
4 Bolts & Nuts properly tighten.
 
5 Valves & components operated/function properly.
 
6 Pipe pressure/hydro test complete & acceptable.
 
7 No leaking evident around fittings or components.
 
8 Piping system properly flushed/cleaned.
                           

No comments:

Post a Comment