PIPE WORK

WELDING WORK (HOT WORK)
NDT/RT/PT/MT
LINE CHECK (ISSUE PUNCH LIST)
CLEAR THE PUNCH LIST
PREPARE FOR HYDRO TEST
FLUSHING/BLOWING/PIGGING
N2 PACK

Thursday, 10 January 2013

E. OTHERS

1 Drawing attached to this checklist.
2 Necessary photographs attached.
I certified that the piping was installed according to the specifications and requirements and comply with the standards.I certified that this documents, photographs, and any other attachments were prepared under my direction or supervision. The information submitted is, to the best of my knowledge and belief, true, accurate and complete.

D. FINALIZING THE INSTALLATION

1 Pipe properly labeled.
 
2 Pipe properly insulated.
 
3 Piping was isolated/blinded.
 
4 Pipe protected from corrosion.
 
5 Proper house keeping done.
 
6 Log Out/Tack Out Procedure done.
 
7 Appropriate permission to return line to service obtained.

C. INSTALLATION

1 Pipes fittings completed.
 
2 Pipe properly supported.
 
3 Valves & components installed properly.
 
4 Bolts & Nuts properly tighten.
 
5 Valves & components operated/function properly.
 
6 Pipe pressure/hydro test complete & acceptable.
 
7 No leaking evident around fittings or components.
 
8 Piping system properly flushed/cleaned.
                           

Wednesday, 9 January 2013

B. PRE-INSTALLATION

1 Line is new.
 
2 Line is re-used.
 
3 Drawings/Layouts submitted & approved.
 
4 Line tracing done.
 
5 Piping was flushed/cleaned.
 
6 Piping was isolated/blinded.
 
7 Log Out/Tack Out Procedure done.

A. IDENTIFICATION

Location of Installation: Vopak Penjuru Terminal (from Berth-2 to Ex-Berth)
Line No.: 6"-1025-SS103
Material Spec.: Stainless Steel 316L
Design Conditions: Pressure: 15.0 Bar
Temperature: 110 Degree C