Inspection & Test Plan (ITP)
ITP
is the minimum requirement of the activities for quality control and
inspection of the field construction work. This Inspection and Testing
Plan outline the extent of witness inspection and its reporting.
CONFLICTING REQUIREMENTS
Should conflicts exist between this specification and other documents, the following order of precedence shall govern:
- Scope of Work
- Data Sheets
- This Specification
- Other Company Specification
- Other Referenced Publications
- Approved for Construction Drawings
- Vendor’s Code
INSPECTION AND TEST PLAN REQUIREMENT
1.
CONTRACTOR and/or its Vendor/Subcontractors shall prepare and execute
all inspection and test. They shall conform to the above mentioned
codes, standards, and project specifications.
2.
CONTRACTOR and/or its Vendor/Subcontractors shall provide all
inspection equipment for inspection activitie s. These activities are to
assure themselves that adequate inspection personnel and back up
equipment are in place in order to expedite their activities speedily so
as not to impact on the construction schedule.
3.
CONTRACTOR and/or its Vendor/Subcontractors shall prepare check sheets
and inspection reports for carrying out the required quality control
checks according to particular discipline work activities. All
inspection and test reports forms shall be specific to the activity and
items inspected.
4.
CONTRACTOR shall also prepare a detailed inspection and test plan
indicating inspection levels (spot witness, witness, hold point, etc),
based on COMPANY definitions herein. The test inspection plan shall
include witness/attendance requirements by COMPANY/MIGAS and/or THIRD
PARTY.
5.
Vendor or Subcontractor shall submit their inspection and test plan
based on the CONTRACTOR’s inspection and test plan document for
CONTRACTOR/COMPANY review and approval.
6. CONTRACTOR
shall generate, maintain, documented, and collate the inspection
records, which is done by them or by its Vendor/Subcontractors. The
system employed shall insure full tractability of records including back
up in accordance to COMPANY requirements. CONTRACTOR shall submit the
originals of all inspection data and other related documents to COMPANY,
as required by the contract terms.
7.
CONTRACTOR and its Third Party shall establish the inspection and test
which are required for obtaining the SKPP (Sertifikat Kelayakan
Penggunaan Peralatan) or Certificate of Worthiness to Utilize Equipment
and SKPI (Sertifikat Kelayakan Penggunaan Instalasi) or Certificate of
Worthiness to Utilize the Installation.
INSPECTION LEVEL DEFINITION
Spot Witness (SW)
Spot
witness inspection is a point during construction activities where
measurement, witnessing of work or inspection normally takes places.
Formal written notification is not required, although oral or informal
memo will normally be given. If the discipline inspector does not
inspect the work at this point, the work may continue. However
inspection data must be recorded, and the CONTRACTOR / Subcontractor is
fully responsible to ensure that this is done before continuing the next
work step.
Witness Point (W)
A witness point is a point in a construction activity where inspection must take place. ONTRACTOR/COMPANY QC Group shall be formally notified in writing of the inspection 24
hours in advance notice is for most accurate schedule) and will
normally attend the inspection. Nevertheless, CONTRACTOR needs to
include schedule of inspections in weekly meetings. On a case by case
basis, the inspection witnessing may be waived. In this case, inspection
may proceed without attendance. However, inspection data must be
recorded and submitted for review and approval. All waivers will be
given in writing prior to inspection execution (jointly approved by
CONTRACTOR and COMPANY).
Hold Point (H)
A
Hold Point is a point in a construction activity where formal written
notification is given of an inspection (24 hours in advance notice is
for most accurate schedule) and work shall not proceed until the
inspection is performed. Nevertheless, CONTRACTOR needs to include
schedule of inspections in weekly meetings. Mandatory attendance is
required.
Approval (A)
A document or drawing, which is to be submitted for approval prior to proceed the activity.
Review and Comment ( R )
A document or drawing, which is to be submitted for review/ comments.
Verification (D)
A document or drawing, which shall be submitted to COMPANY/CONTRACTOR for report/ comments.
COORDINATION
Quality Control and Inspection by CONTRACTOR
For
the items marked with “ SW “ and “ W “ under column “CONTRACTOR”, the
quality control and inspection will be conducted by CONTRACTOR at their
own responsibility. However, COMPANY shall have the right to inspect any
works done by CONTRACTOR or Vendor at any time (except for “ W ”, a
written notification from CONTRACTOR is required).
Inspection Hold Point
For
item marked with “ H “ under column of COMPANY and CONTRACTOR,
CONTRACTOR shall notify COMPANY in writing of the inspection scheduled
date and time. Witnessing shall be jointly performed by CONTRACTOR and
COMPANY. CONTRACTOR can not proceed the next work step activity until
the inspection and measurement or test has been witnessed and approved
by all attending parties.
Notification of Inspection
CONTRACTOR shall give a written notification to COMPANY for attending the inspection/testing.
Document Approval
For
item marked with “ A “ under column “COMPANY”, CONTRACTOR shall submit
documents, drawing, etc. to COMPANY. For item marked with “ A “ under
column “CONTRACTOR”, Vendor shall submit documents, drawing, etc. to
CONTRACTOR for approval. Inspection shall not be conducted before
COMPANY approves the required documents.
Document Review
For
item marked with “ R “ under column “COMPANY”, CONTRACTOR will submit
documents, drawing, etc. to COMPANY for review / comment. For item
marked with “ R “ under column “CONTRACTOR”, Vendor shall submit
documents, drawing, etc. to CONTRACTOR for review / comment.
Document Verification
For
item marked with “ D “ under column “COMPANY”, CONTRACTOR shall submit
documents, drawing, etc. to COMPANY for a report and/ or comments (if
required). CONTRACTOR shall accommodate COMPANY’s comments (if any). For
item marked with “ D “ under column “CONTRACTOR”, Vendor shall submit
documents, drawing, etc. to CONTRACTOR for verification and review and
or report.
No comments:
Post a Comment