ITP
is the minimum requirement of the activities for quality control and
inspection of the field construction work. This Inspection and Testing
Plan outline the extent of witness inspection and its reporting.
CONFLICTING REQUIREMENTS
Should conflicts exist between this specification and other documents, the following order of precedence shall govern:
- Scope of Work
- Data Sheets
- This Specification
- Other Company Specification
- Other Referenced Publications
- Approved for Construction Drawings
- Vendor’s Code
INSPECTION AND TEST PLAN REQUIREMENT
1.
CONTRACTOR and/or its Vendor/Subcontractors shall prepare and execute
all inspection and test. They shall conform to the above mentioned
codes, standards, and project specifications.
2.
CONTRACTOR and/or its Vendor/Subcontractors shall provide all
inspection equipment for inspection activitie s. These activities are to
assure themselves that adequate inspection personnel and back up
equipment are in place in order to expedite their activities speedily so
as not to impact on the construction schedule.
3.
CONTRACTOR and/or its Vendor/Subcontractors shall prepare check sheets
and inspection reports for carrying out the required quality control
checks according to particular discipline work activities. All
inspection and test reports forms shall be specific to the activity and
items inspected.
4.
CONTRACTOR shall also prepare a detailed inspection and test plan
indicating inspection levels (spot witness, witness, hold point, etc),
based on COMPANY definitions herein. The test inspection plan shall
include witness/attendance requirements by COMPANY/MIGAS and/or THIRD
PARTY.
5.
Vendor or Subcontractor shall submit their inspection and test plan
based on the CONTRACTOR’s inspection and test plan document for
CONTRACTOR/COMPANY review and approval.
6. CONTRACTOR
shall generate, maintain, documented, and collate the inspection
records, which is done by them or by its Vendor/Subcontractors. The
system employed shall insure full tractability of records including back
up in accordance to COMPANY requirements. CONTRACTOR shall submit the
originals of all inspection data and other related documents to COMPANY,
as required by the contract terms.
7.
CONTRACTOR and its Third Party shall establish the inspection and test
which are required for obtaining the SKPP (Sertifikat Kelayakan
Penggunaan Peralatan) or Certificate of Worthiness to Utilize Equipment
and SKPI (Sertifikat Kelayakan Penggunaan Instalasi) or Certificate of
Worthiness to Utilize the Installation.
No comments: