Please
kindly refer to attached Overall Schedule & Project Organization Chart_
Rev 1.1_20130828 for your perusal.
As per our
Internal Kick Off Meeting, please kindly refer to below for the key action
items of the projects for your attention & follow up:
Project
General:
1.
Communication
Channel, Organization Chart & Overall Schedule to be submitted to MES by
end of August 2013
2.
1st
Monthly Progress Report to be submitted to MES by end of September 2013,
cut-off date is 25 of the month
SAFETY HEALTH & ENVIRONMENT
Engineering:
1.
Vender
Document List (VDL) to be submitted to MES by end of August 2013
2.
General
Assembly, Design Calculation, Material Specification & BQ for Purchasing of
Main Plates to be ready by 16 September 2013
Procurement:
1.
PO
to be issued for purchasing of Main Plates by 20 September 2013
2.
Estimate
to Arrive (ETA) of Main Plates in Singapore shall be 1st December
2013
Fabrication:
1.
Fabrication
of Main Plates to be started in 1st Week of December 2013
2.
1st
lot of Bottom, Roof & Shell Plates for TK-2961 to be ready to deliver to
job site by end of December 2013 w/ Blasting & Painting
3.
Shop
Assembly of Hopper (TK-2455) to be completed with NDE & Pneumatic Test by
end of March 2014
Construction:
1.
Site
Mobilization is on 2nd of January 2014
2.
Commencement
of construction works for TK-2961 to be on 3rd January 2014
3.
Site
Assembly of Hoppers (TK-2410) to be completed with NDE & Pneumatic Test by
end of March 2014
4.
Site
Construction of CRT (TK-2961) to be completed with NDE & Hydrostatic Test
by end of May 2014
5.
Site
Construction of CRT (TK-2261 & TK-2990) to be completed with NDE &
Hydrostatic Test by end of June 2014