Monday 3 March 2014

KICK OFF MEETING

Please kindly refer to attached Overall Schedule & Project Organization Chart_ Rev 1.1_20130828  for your perusal.

As per our Internal Kick Off Meeting, please kindly refer to below for the key action items of the projects for your attention & follow up:

Project General:
1.       Communication Channel, Organization Chart & Overall Schedule to be submitted to MES by end of August 2013
2.       1st Monthly Progress Report to be submitted to MES by end of September 2013, cut-off date is 25 of the month

 SAFETY HEALTH & ENVIRONMENT

Engineering:
1.       Vender Document List (VDL) to be submitted to MES by end of August 2013
2.       General Assembly, Design Calculation, Material Specification & BQ for Purchasing of Main Plates to be ready by 16 September 2013

Procurement:
1.       PO to be issued for purchasing of Main Plates by 20 September 2013
2.       Estimate to Arrive (ETA) of Main Plates in Singapore shall be 1st December 2013

Fabrication:
1.       Fabrication of Main Plates to be started in 1st Week of December 2013
2.       1st lot of Bottom, Roof & Shell Plates for TK-2961 to be ready to deliver to job site by end of December 2013 w/ Blasting & Painting
3.       Shop Assembly of Hopper (TK-2455) to be completed with NDE & Pneumatic Test by end of March 2014

Construction:
1.       Site Mobilization is on 2nd of January 2014
2.       Commencement of construction works for TK-2961 to be on 3rd January 2014
3.       Site Assembly of Hoppers (TK-2410) to be completed with NDE & Pneumatic Test by end of March 2014
4.       Site Construction of CRT (TK-2961) to be completed with NDE & Hydrostatic Test by end of May 2014

5.       Site Construction of CRT (TK-2261 & TK-2990) to be completed with NDE & Hydrostatic Test by end of June 2014